Let’s reflect on the past 12 months.

Further to these troubled times we thought we would reflect on some fantastic projects over the last 12 months.

Here we show a new water main installed to over 100 stores in a major shopping centre.

The velocity and required flow rates for the existing shop units were calculated and taken into consideration for the new designed pipework.

A 108mm water pipe was ran along the roof of the shopping centre installed on a big foot system.

Insulated with Kooltherm lagging and a final coating of PIB for weather and UV resistance. Over 1km of pipe was installed and over 120 shops were connected.

There was no trading interruption on a tight thirteen week schedule. The client was thrilled with the installation and commended Dante Group on the delivery of the project.